(Revised
1.1
Purpose
The purpose of these requirements is to define minimum standards and procedures for the design, permitting, construction and maintenance of drainage facilities. They also provide standard procedures for estimating flow and establishing allowable runoff criteria for developed property.
These requirements present minimum storm water standards
that apply to physical development within the City. Compliance with these standards does not
relieve the Engineer of the responsibility to use sound professional
judgment. These standards are intended
to assist, but not to substitute for, design by a registered Professional
Engineer licensed in the State of
1.2 Purpose of a
drainage facility
· Limit peak post-development stormwater flows
· Treat storm water to improve water quality
· Mitigate the impacts of increased runoff due to urbanization
· Maximize infiltration and minimize runoff from developed property
· Facilitate groundwater recharge
· Protect groundwater quality
State or Federal law may preempt these standards and require more stringent or additional requirements. Alternatives to standard plans, specifications, and design details found in these design requirements may be accepted if they meet or exceed the performance of the standards.
1.3 Regulatory
Authority
Under Pocatello City Ordinance 17.48, Site Plan Review, the City shall approve all designs, plans, and construction requirements.
1.4 Required Elements
for Stormwater Management Plans
Stormwater management plans shall be submitted for all commercial, industrial, residential, and subdivision developments. Storm water management plans shall contain:
· Topographic survey of the development showing existing drainage and conveyance systems
· Topographic map showing delineation of all basins tributary to the area affected by the proposed development
· Peak flow rate calculations for all outlets and drainage works (pre- and post-development, as applicable)
· Runoff volume calculations for all proposed and existing storage facilities (pre- and post-development, as applicable)
· Plan of new or modified drainage systems, including dimensions and volume calculations
· Grades of all impervious surfaces
· Flood routing, flow and volume computations for the 100-year flood through the site (includes all contributing areas)
· Drainage report which includes basis for design, narration for the design, and operation of the drainage system. For multi-phase developments, the drainage report must include pertinent data from all phases.
· Copies of any easements, permits, or discharge agreements
· Landscape plan
· Operation and maintenance plan, with the name of the responsible contact, as well as company specifications and recommended maintenance for equipment or systems used in the drainage system.
· All calculations are to be computed in a tabular format acceptable to the City. The computations shall be submitted in paper and electronic formats
1.5 Stormwater
management design criteria
1.5.1 Water Quantity
Design Storm Criteria for Surface Water Management
The Rational Method for determining peak flow rates and volumes should be used for developments affecting areas not greater than 100 acres. For larger developments (greater than 100 acres), the Natural Resources Conservation Service (NRCS) method, TR-55 should be used. Other hydrologic methods may be acceptable for determining runoff rate and volumes, however, if an alternate hydrologic method is selected, the design professional shall obtain written approval from the City prior to beginning hydrology studies.
The post-development runoff flow rate from any proposed land development shall be less than or equal to the calculated pre-development runoff rate for any storm up to the 10-year event. Pre- and post-development rates shall be calculated for the 10- and 100-year events.
Outlets from detention facilities must be adjustable and designed to replicate pre-development discharge conditions for up to 10-year storm events. Overflows must pass the 100-year event without failing.
Minor conveyance systems (subsurface pipe networks, inlets, etc.) shall be designed to accommodate the peak flow of the 10-year event. Major conveyance systems (streets, channels, etc.) shall be designed to accommodate the peak flow of the 100-year event.
The stormwater runoff from the proposed development cannot be diverted and released to any downstream property that, prior to the proposed development, would not have received any runoff unless the downstream property owner provides:
1) easement
2) on-site detention meeting the criteria presented in this document
3) written approval from the City certifying the capacity of receiving infrastructure
1.5.2 Water Quality
Design Storm Criteria
Different standards apply to surface and subsurface management of stormwater. For all controls, it is presumed that these standards are met when:
1. Applicable nonstructural practices for source control and pollution prevention are implemented. Source controls prevent pollutants from entering storm water runoff and may include practices such as parking lot sweeping and spill prevention;
2. Stormwater best management practices, BMPs, are sized to capture and treat runoff
3. Stormwater management BMPs are maintained as designed.
1.5.3 Subsurface
Management of Stormwater
Storm water runoff can also be disposed of underground by using seepage beds, infiltration basins, and infiltration swales. Infiltration practices shall be designed to ex-filtrate the entire water volume for a 10-year event and pass the 100-year event. Source controls should be in place to protect ground water in case of accidental hazardous material or waste spills.
1.5.4 Water quality
design criteria during construction
For new development projects, water quality BMPs shall be implemented on all disturbed areas. Stormwater BMPs shall be designed to remove the average annual load of total suspended solids (TSS). The removal rate for TSS during construction and until the site is stabilized, is 70%. Hazardous materials cannot leave the site nor may they be allowed to impact groundwater. The design storm to meet these water quality criteria is the 2-year event.
1.5.5 Water quality
design criteria for post-development
For new development projects, water quality BMPs shall be implemented on all impervious and disturbed areas. All other pervious areas must be stabilized to protect against erosion. Stormwater BMPs shall be designed to remove 85% of the total suspended solids (TSS) or current NPDES requirements.
1.5.6 Water quality
design for high-risk land uses
Projects that fall into certain land use categories may generate higher than allowable pollutant concentrations. These land use categories are considered to be potential significant sources of pollutants and include the following:
· Industrial facilities that are required to obtain a NPDES industrial stormwater permit
· Vehicle salvage yards (including auto recycler facilities)
· Vehicle fueling facilities
· Vehicle parts stores
· Fleet storage areas (cars, buses, trucks)
· Vehicle service, maintenance and equipment cleaning areas
· Road salt storage and loading areas (if exposed to rainfall)
· Commercial nurseries
· Outdoor storage and loading/unloading areas of hazardous substances
· Bulk material sales (landscape, rock/sand products)
Stormwater discharges from land uses with higher potential pollutant loads require the following:
· Source reduction (pollution prevention) BMPs
· Pretreatment systems for the expected pollutants (besides sediment) such as catch basin inserts, oil/water separators, drainage channels, biofiltration swales, and/or deep sump catch basins.
· Proposed site activities should be evaluated for the potential to contribute pollutants to storm water. Applicable BMPs shall be identified in the facility’s Operation and Maintenance Plan.
1.6 Redevelopment
Standards
A redevelopment project is a project that requires a building permit and proposes to add, replace and/or alter impervious surface (other than routine maintenance, resurfacing, or repair). The following requirements apply to redevelopment projects:
1.6.1 Water Quantity
The applicant shall evaluate the existing stormwater system to determine if the system has sufficient capacity for additional runoff from the proposed redevelopment project.
A plan shall be submitted for a redevelopment project when there is an increase in impervious surface greater than 100 ft2 or greater than 10% of the existing impervious area (whichever is greater) to the tributary area of the storm water facility. A plan is also required when an existing drainage system is modified in any way.
1.6.2 Water Quality
For all projects requiring a building permit, an Operation and Maintenance Plan for the drainage system will be required. The O&M Plan shall include source controls for all on-site activities that can contribute pollutants to stormwater runoff. Tenant improvements that do not affect drainage, single-family house projects, and residential subdivisions with 4 or fewer living units are exempted from this requirement
If the redevelopment project is less than or equal to 5000 ft2, and involves a land use with potential higher pollutant loads, the system shall be retrofitted to manage the particular pollutants associated with the land use.
If the redevelopment project is greater than 5000 ft2, then the applicable % TSS removal rate from section 1.5.5 is required. The TSS removal rate applies to surface discharge of storm water only. Subsurface disposal is prohibited unless the applicant can demonstrate that its implementation meets applicable and current Idaho DEQ groundwater protection requirements. If the land use has a potential for higher pollutant loads, additional pretreatment may be required.
If it is not practicable to meet the applicable redevelopment standards, the applicant must request a variance and new retrofitted or expanded stormwater management systems must be designed to improve existing conditions.
1.7 Determining Peak
Discharge, Peak Volume, and the Water Quality Volume
1.7.1 Water Quantity
The following is a list of the basic steps to be taken in order to calculate the peak discharge rates from pre- and post-development conditions and the volume of stormwater that must be retained onsite to control peak discharge rates from specified storms. The Rational Method is presented. NRCS TR-55 is also permitted. Other hydrologic methods may be accepted for determination of runoff rate and volume; however the design professional shall obtain written approval from the City Engineer prior to beginning hydrologic studies for the project if an alternate hydrologic method is used.
The Rational Method must be used for basins less than 100 acres. Alternate methods may be permitted for basins greater than 100 acres.
Calculations should be presented in an easily tabular format and submitted on paper and on disk. For TR-55, HEC-1, and other computer modeling techniques that may be approved by the City, the Engineer shall supply the City with the base data, assumptions and input and output files in electronic and paper format.
1.8 Steps for
Determining Peak Discharge (Rational Method)
![]()
Where:
Qp = peak discharge (cfs)
C = dimensionless runoff coefficient
i = average rainfall intensity (in./hr) for a duration equal to the time of concentration and for the recurrence interval chosen for design storm (2-year treatment, 10-year conveyance, and 100-year overflow)
A = basin area (acres)
1) Calculate the site area (A):
Use USGS topographic maps, surveys, and other available information. Show delineated basin boundaries on maps or drawings submitted to the City for review and approval.
2) Determine the pre and post development composite runoff coefficient (C) for each basin:
This value is obtained from the Runoff Coefficient table for pre-development and post-development conditions. Composite C values shall be computed from Table 1.8.2, and fall within the ranges given in Table 1.8.1 for the pre and post development land use. For mixed surfaces, determine a weighted coefficient using the following formula:

TABLE 1.8.1 Accepted Range of Composite Runoff Coefficients
|
Description of Area |
Runoff Coefficients |
|
Business |
|
|
Downtown areas |
0.70-0.95 |
|
Neighborhood areas |
0.50-0.70 |
|
Residential |
|
|
Single-family areas |
0.30-0.50 |
|
Multiunits, detached |
0.40-0.60 |
|
Multiunits, attached |
0.60-0.75 |
|
Residential (suburban) |
0.25-0.40 |
|
Apartment dwelling areas |
0.50-0.70 |
|
Industrial |
|
|
Light areas |
0.50-0.80 |
|
Heavy areas |
0.60-0.90 |
|
Parks, cemeteries |
0.25 |
|
Playgrounds |
0.35 |
|
Railroad yard areas |
0.40 |
TABLE 1.8.2 Runoff Coefficients For Use In Computing Composite
|
Description of Area |
Runoff Coefficient |
|
Unimproved areas |
0.25 |
|
Streets |
|
|
Asphaltic |
0.95 |
|
Concrete |
0.95 |
|
Brick |
0.85 |
|
Drives and walks |
0.85 |
|
Roofs |
0.95 |
|
Lawns; Sandy Soil: |
|
|
Flat, 2% |
0.10 |
|
Average, 2-7% |
0.15 |
|
Steep, 7% |
0.20 |
|
Lawns; Heavy Soil: |
|
|
Flat, 2% |
0.17 |
|
Average, 2-7% |
0.22 |
|
Steep, 7% |
0.35 |
3) Calculate the time of concentration in minutes (tc)
The time of concentration (in./hr) over a duration equal to the time of concentration for the contributing area can be estimated using Kirpich’s Equation as follows:

The minimum tc required for 100-year spillway flows is 30 minutes (i = 3.76 in/hr)
The minimum tc required for all other design flows is 10 minutes (i = 3.67 in/hr)
Where:
tc = time of concentration (min)
L = length of travel (ft)
S = slope (ft/ft)
4) Determine the average rainfall intensity (i):
This value is obtained from the intensity-duration-frequency
curves for
5) Calculate
the peak discharge (Qp) for each basin outlet
a) Qp
= C * i * A
b) Calculate
pre-development Qp
c) Calculate
post-development Qp

Figure 11-1:
1.9 Steps to
Calculate Onsite Storage volumes for Control of Peak Discharge Rates
![]()
Where:
Vr = Volume of runoff (ft3)
C = dimensionless runoff coefficient
A= contributing area to storage site (ft2)
1) Calculate the contributing drainage area (A)
Use value from 1) above.
2) Determine the average rainfall intensity (i)
Use the 10-year 3 hour event for detention (i = 0.62)
Use the 2-year 3 hour event for retention (i = 0.27)
3) Determine the storm duration (T)
For volume computations, T = 3 hours
4) Determine the runoff coefficient (C)
Use value from step 2 above. Compute an overall composite C if more than one basin contributes to the storage facility.
5)
![]()
Calculate the total volume of runoff (V) to be detained
6)
![]()
Calculate the volume of retention required for treatment:
1.10 Design
Calculations
Show design calculations to justify the size of subsurface piping, storm sewer inlets, and downstream capacity if the proposed drainage works reroute the pre-development flow path. Appurtenances shall be designed to the following criteria:
Facility Design Storm
On-site
retention 2-year
On-site detention 10-year
Storm sewer piping & inlet 10-year
Constrictions at RR tracts 100-year
Bridges, streets, and open
channels 100-year
Storm drains shall be designed to provide the required capacity without surcharging the line. Storm drain outlets shall be designed to function as a part of the build-out drainage system. Where major trunk lines are not available, a temporary outlet and a future connection to the proposed trunk storm drain shall be provided. This is to permit effective drainage until the development and construction of a completed storm drain system. Storm sewers shall not be designed with a velocity of less than 2 fps. When a pipe size has been established, it shall not be reduced downstream. Maximum manhole spacing is 400 feet. Manholes will also be required at changes in grade, pipe size, or alignment. Curved pipe will not be permitted for 36-inch pipe or less. Inlets shall be designed to intercept 100% of the total runoff delivered to the inlet in the 10 year storm event. Manholes shall be required at the upstream terminus of all storm sewer lines.
1.11
Additional Criteria
1) Storage deeper than 1.0 feet shall require an outlet mechanism that will facilitate full discharge within 24 hours at a rate not to exceed 0.1 cfs per acre (of the total development).
2) Spillway height shall not exceed 6.0 feet for any facility.
3) All portions of central storage basins must drain towards outlet.
4) Private detention facilities: Minimum bottom grade = 1% maximum with side slope = 4:1 and drained to the outlet. City Parks: graded to drain to outlet; 10:1 side slopes for mowing access.
5) Provide minimum of 1-foot freeboard above high water design elevation on all sides of the detention area, including lowest development gutter flow line.
6) The outlet pipe must be sized to pass the constant flow rate necessary to drain the pond in 24 hours at a rate not to exceed 0.1 cfs per acre of the development, and be connected to the same stormwater outfall that the basin drained to before development unless approved otherwise. The outlet pipe and the emergency spill way together shall be designed to pass the 100-year event for the entire drainage tributary to the facility.
7) Discharge requirements:
(a) Detention volume must be disposed of within 24 hours.
(b) If pumps are used, provide automatic switch control with vertical float control mechanisms. Pumps shall be accessible when lagoon is full. Screen pump inlet with ¾ inch stainless steel mesh.
8) Storage facility outlets shall be located above the elevation of the storage required to retain and treat for the 2-year event. Maximum outlet invert height shall be 12 inches.
9) Retention basin designs shall be submitted to the City for review. Retention ponds will be sized typically by calculating the required volume for a detention facility in the same location, and multiplying the resulting volume by 10 if there is no positive outlet.
10) All disturbed soils shall be stabilized by seeding and irrigation until such vegetation is established.
1.12 References
Stormwater Master Plan. Prepared by Schiess and
Associates, Consulting Engineers. Prepared for the
City of
State of